Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Barrett Station (Phase 2 Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, with an addition in the amount of $62,146.38, Job No. 23/0337-4, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%, MWBE Participation: 39.03%. | Community Exchange
PolicyCountyOur Government
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Barrett Station (Phase 2 Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, with an addition in the amount of $62,146.38, Job No. 23/0337-4, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%, MWBE Participation: 39.03%.
Harris County is reviewing a $62,146.38 contract increase for drainage work in the Barrett Station Phase 2 subdivision in Precinct 3.
Harris County Commissioners Court is reviewing a contract change with Texas Materials Group, Inc. The change adds $62,146.38 to the cost of drainage improvements in the Barrett Station Phase 2 subdivision in Precinct 3. The project met its minority and women-owned business goal, with 39.03% participation against a 31% target. The item was introduced on August 11, 2026.
This contract change affects drainage work in the Barrett Station Phase 2 area of Precinct 3. Residents near Barrett Settlement and St. Charles Place may see how public funds for local flood infrastructure are being managed.