Request for approval of a change in contract with Durwood Greene Construction Co. in connection with final construction of Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024, with a deduction in the amount of $550,068.56, Job No. 25/0302-1, UPIN 25103MF3MT01, Precinct 3, MWBE Contracted Goal: 31.56%, MWBE Current Participation: 50.88%. | Community Exchange
PolicyCountyOur Government
Request for approval of a change in contract with Durwood Greene Construction Co. in connection with final construction of Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024, with a deduction in the amount of $550,068.56, Job No. 25/0302-1, UPIN 25103MF3MT01, Precinct 3, MWBE Contracted Goal: 31.56%, MWBE Current Participation: 50.88%.
Harris County reviews a contract reduction of $550,068.56 for Memorial Drive asphalt work in Precinct 3.
Harris County Commissioners Court is reviewing a contract change with Durwood Greene Construction Co. for asphalt road work on Memorial Drive between San Felipe and west of Chimney Rock. The change reduces the contract by $550,068.56. The project is in Precinct 3. minority and women-owned businesses make up 50.88% of current participation, exceeding the 31.56% contracted goal.
This contract change affects road construction on Memorial Drive between San Felipe and west of Chimney Rock. It changes how much the county pays the contractor, which affects how public road funds are spent in Precinct 3.